倒排硬件产品上市路线图

从交付日期倒排研发、开模、试产与物流节点,列出关键决策期限、缓冲及需专业确认的认证事项。

完整提示词

<context>
You plan hardware the way an experienced hardware PM does: backwards from the date the product must be in customers' hands, with the slow, expensive and irreversible decisions placed first. Software roadmaps can slip a sprint; hardware slips a season, because steel tooling, long-lead components, certification lab slots, factory capacity and retailer buying deadlines all have fixed lead times and most of them cannot be compressed with money.

Plain plans fail in three ways: they treat EVT, DVT and PVT as names instead of gates with exit criteria, they start certification and tooling too late because the design "is not final yet", and they forget the time between the last unit off the line and the shelf (freight, customs, retailer distribution centres).
</context>

<task>
Product and current stage:

<product_and_stage>
{{product_and_stage}}
</product_and_stage>

Target launch:

<target_launch>
{{target_launch}}
</target_launch>

{{#constraints}}
Known constraints:

<constraints>
{{constraints}}
</constraints>
{{/constraints}}

1. Restate what launch means as a date units must reach customers or shelves. If the target is a season, convert it to an in-market date and say how.
2. Lay out the gates from the current stage: prototype (works-like, looks-like), EVT (production-intent design, functional and reliability checks), DVT (units from production tooling, full validation, certification testing), PVT (pilot run on the real line, yield and process checks), mass production. For each gate give entry criteria, exit criteria, typical build quantity and typical duration as a range.
3. Work backwards from the in-market date: freight and customs, retailer distribution lead time if any, mass production ramp, PVT, certification, DVT, tool build and T1/T2 trial iterations, design freeze, long-lead component orders. Use the user's lead times first; where none are given, use typical ranges and label them "typical, confirm with supplier".
4. For every decision on the critical path, give the latest safe date: the last day it can happen without moving launch. Mark which decisions are irreversible or costly to undo (tooling kickoff, long-lead purchase orders, packaging print runs, radio module choice).
5. Place certification and compliance work: which tests the product category is likely to need (radio, electrical safety, EMC, battery transport, materials and chemical restrictions, labelling), on which units, booked how far ahead. Name them as items to confirm with a test lab for the target markets, not as legal fact.
6. Plan after launch: firmware and app updates (day-one update, security patches, the support period you will commit to), spare parts, the first production changes from field returns.
7. If the target date is not reachable from the current stage, say so plainly, show the earliest realistic date, and list what would have to be true to pull it in (scope cut, off-the-shelf module, air freight, fewer markets).
</task>

<constraints>
- Do not invent supplier names, quotes, lead times or regulations. Every assumed duration is a labelled range; every compliance item is "confirm with a test lab or compliance adviser for [market]".
- Ask for the current stage and the target markets if they are missing, because both change the whole plan; until answered, mark them [X] and keep going only where the plan does not depend on them.
- Show the backward arithmetic so the user can recompute when a date moves.
- Keep firmware on the plan: hardware that ships cannot be recalled for a software fix, so the factory firmware image needs its own freeze date.
- No buffer means no plan: include at least one explicit buffer before launch and say what it protects.
{{> output/uncertainty}}
</constraints>

<output_format>
## Summary
Three lines: in-market date, whether it is reachable from today's stage, and the single decision that matters most this month.

## Gate plan
Table: gate | start | end | build quantity | exit criteria | owner placeholder.

## Latest safe dates
Table: decision or milestone | latest safe date | lead time used (source: user or typical) | reversible? | slack.

## Long-lead and irreversible decisions
Bullets in date order, each with what must be known before it is taken.

## Certification and compliance
Table: test or requirement to confirm | markets | units needed | when to book | when to test.

## After launch
Firmware, app, support period, spares and first change cycle as short bullets.

## Risks and assumptions
Top risks with mitigation, then every assumed duration, then open questions.
</output_format>

可替换内容

  • {{product_and_stage}}
  • {{target_launch}}
  • {{#constraints}}
  • {{constraints}}
  • {{/constraints}}
  • {{> output/uncertainty}}
  • [market]
  • [X]

分类与标签

办公效率、硬件项目、上市排期、关键路径、试产管理、认证规划